CONSTRUCTION WORK ON SECOND NIGER BRIDGE TO BE COMPLETED SOON
The construction work on the Second Niger Bridge will soon be completed as work has reached forty four point six percent.
The Federal Controller of works in Anambra State, Mr Innocent Alumonah, confirmed the progress of work on the bridge that is linking Asaba in Delta State and Onitsha in Anambra State.
Mr. Alumonah said the construction firm, had also completed about eighty five piles of 914 millimeter in diameter in different axis.
He said the contract for the early work stage was awarded in October 2016 while work commenced in November 2017.
MIRIAM ESONWUNE
More Stories
SOLUDO WOULD NOT CIRCUMVENT LG FINANCIAL AUTONOMY— OBIOGBOLU
REPORTER: BEN ILECHUKWU Anambra State Government says it will not violate the Supreme Court judgment on financial autonomy granted to...
FG DISTRIBUTES RICE TO VULNERABLE CITIZENS IN AWKA
REPORTER: CHRIS OBILERI President Bola Ahmed Tinubu says his administration will continue to accord priority to the plight of the...
SECURITY AGENTS RESCUE SIX ABDUCTED JOURNALISTS IN ANAMBRA
REPORTER: KEVIN EKEDIEGWU Joint security forces in Anambra State have successfully rescued six members of the media crew who were...
BOOKS EXTORTION: ABIA ASSEMBLY MOVES TO STOP PRIVATE SCHOOLS
REPORTER: UZOMA NWANKWO The Abia State House of Assembly has resolved to stop private schools from compelling parents to buy...
WORLD MENTAL ILLNESS DAY: MEDICAL EXPERTS CAUTION YOUTHS AGAINST SUBSTANCE ABUSE, TASK GOVT ON JOB CREATION
REPORTER: CYNTHIA EGWU Just like in many cities in the country, people with mental illness, mostly youths, are seen in...
PROVIDE CONDUCIVE WORK ENVIRONMENT — MENTAL HEALTH EXPERT TELLS EMPLOYERS
REPORTER: JOHN MADUAGWU Employers of labour have been advised to provide a conducive work environment for Nigerian workers to enhance...